Bet Haverim

title.png
Meeting with Rabbi Wolfe January 17, 2020 to begin discussions of the Bet Haverim Sanctuary Stained Glass Projecyt
Meeting with Rabbi Wolfe January 17, 2020 to begin discussions of the Bet Haverim Sanctuary Stained Glass Projecyt
Roots in Heaven
Roots in Heaven

The final design for the stained glass

Roots in Heaven left detail
Roots in Heaven left detail
Roots in Heaven right detail
Roots in Heaven right detail

Making the Pattern

 Working on the patterns

Working on the patterns

January 6, 2022
January 6, 2022

Checking the blueprints enlarged from the Illustrator Files

 Preparing the blueprints and building a 12’x10’ table

Preparing the blueprints and building a 12’x10’ table

 Michelle begins to lay out the patterns

Michelle begins to lay out the patterns

January 7, 2022
January 7, 2022
January 7, 2022
January 7, 2022

Sizing and positioning the patterns

Januay 8, 2022
Januay 8, 2022

Stretching to work on the center of the composition

January 8, 2022
January 8, 2022

Michelle performs some difficult gymnastics, working on the patterns.

January 8, 2022
January 8, 2022

Generating the diagonal lines.

January 9, 2022
January 9, 2022

Michelle working on the pattern

January 9, 2022
January 9, 2022

Michelle drawing pencil lines on the full-size pattern

January 9, 2022
January 9, 2022

Continue work on the pattern

January 10, 2022
January 10, 2022

Beginning to think about the glass is part of making the pattern.

January 10 ,2022
January 10 ,2022

Calculating the materials that will be needed to manufacture the stained glass panels. Our glass is mouth-blown in Waldsassen, Germany and shipped to us through New York.

January 21, 2022
January 21, 2022

Work continues on the patterns.

Glass Cutting Begins

After finishing the patterns, Michelle begins the process of choosing the glass and beginning to cut the pieces for the first panel.

 Michelle cuts the first piece of glass.

Michelle cuts the first piece of glass.

 Michelle, in one of the glass rooms, starts choosing the colors and sheet glass to use for the windows.

Michelle, in one of the glass rooms, starts choosing the colors and sheet glass to use for the windows.

 Michelle working in her studio surrounded by expanding piles of scrap glass, samples and full sheets.

Michelle working in her studio surrounded by expanding piles of scrap glass, samples and full sheets.

 Work proceeds one piece at a time.

Work proceeds one piece at a time.

 The pieces are laid out on a duplicate of the pattern as they are cut out.

The pieces are laid out on a duplicate of the pattern as they are cut out.

 Working on the full size pattern.

Working on the full size pattern.

 The window grows as Michelle cuts the pieces.

The window grows as Michelle cuts the pieces.

 All the unresolved questions need to be answered now.

All the unresolved questions need to be answered now.

 Michelle among her piles of glass.

Michelle among her piles of glass.

 The window continues to grow as Michelle continues to cut.

The window continues to grow as Michelle continues to cut.

 Michelle continues the process of choosing each piece of glass, beginning the second panel.  Apparently,, Michelle is making the window. David’s time will come.

Michelle continues the process of choosing each piece of glass, beginning the second panel. Apparently,, Michelle is making the window. David’s time will come.

 But until then, it’s just Michelle.

But until then, it’s just Michelle.

Cutting Continues

UNADJUSTEDNONRAW_thumb_b7d0.jpg
UNADJUSTEDNONRAW_thumb_b7c5.jpg
UNADJUSTEDNONRAW_thumb_b7e7.jpg
UNADJUSTEDNONRAW_thumb_b7e8.jpg
UNADJUSTEDNONRAW_thumb_b7f4.jpg
UNADJUSTEDNONRAW_thumb_b7f6.jpg

March 24, 2022

Cuttimg continues on the first three panels.

 Michelle working in her studio

Michelle working in her studio

 Michelle cuts a piece of glass for the windows

Michelle cuts a piece of glass for the windows

UNADJUSTEDNONRAW_thumb_b815.jpg
 Newly constructed glass easel for easier display of colors.

Newly constructed glass easel for easier display of colors.

UNADJUSTEDNONRAW_thumb_b807.jpg
 Pieces are laid out as cutting continues.

Pieces are laid out as cutting continues.

 The cutting of the leaves begins in order to apply the painted decoration.

The cutting of the leaves begins in order to apply the painted decoration.

 Michelle at her table covered in scrap.

Michelle at her table covered in scrap.

April 3, 2022

Glass cutting continues. Leaves are covered with resist in preparation for painting. Palette of colors continues to expand as studio fills with glass.

 Michelle bends over the cutting table while she cuts out the leaves.

Michelle bends over the cutting table while she cuts out the leaves.

 Leaves are laid on the pattern.

Leaves are laid on the pattern.

 Beginning of a new panel.

Beginning of a new panel.

 Leaves are covered with resist.

Leaves are covered with resist.

 Proliferation of colors and mounds of scrap.

Proliferation of colors and mounds of scrap.

 Scrap glass.

Scrap glass.

Assembly Begins

Glass cutting continues as Michelle begins on the fourth panel. David begins the assembly of the first panel as each piece of glass is built into the lead matrix.

UNADJUSTEDNONRAW_thumb_b869.jpg
 A window takes shape on the 12’ long work board.

A window takes shape on the 12’ long work board.

 Michelle, meanwhile is in the glass room working on the light table, cutting glass.

Michelle, meanwhile is in the glass room working on the light table, cutting glass.

 The fourth panel begins to take shape as Michelle cuts out and lays down the pieces of glass for it.

The fourth panel begins to take shape as Michelle cuts out and lays down the pieces of glass for it.

 Detail of the assembly shows the pieces of lead came forming the matrix of metal to hold the glass together.

Detail of the assembly shows the pieces of lead came forming the matrix of metal to hold the glass together.

 A window on the assembly table.

A window on the assembly table.

April 8, 2022

Cutting continues.

Assembly continues.

Painting continues.

 Cutting continues.

Cutting continues.

 Partially assembled panels

Partially assembled panels

 David is assembling a panel.

David is assembling a panel.

 David works on preparing the leaf pieces for painting.

David works on preparing the leaf pieces for painting.

 Working on the preparation for painting.

Working on the preparation for painting.

 Two panels laid out during cutting.

Two panels laid out during cutting.

 Another panel laid out ready for assembly.

Another panel laid out ready for assembly.

 Michelle showing off her cutting skills.

Michelle showing off her cutting skills.

April 12, 2022

Painting the leaves

 Michelle applies paint to the leaves after the composition and lay out has been burnished on and cut out with the xacto knife.

Michelle applies paint to the leaves after the composition and lay out has been burnished on and cut out with the xacto knife.

 Resist is pulled off and the painted letters are touched up.

Resist is pulled off and the painted letters are touched up.

 Michelle examines a leaf while touching up the paint.

Michelle examines a leaf while touching up the paint.

 A leaf is painted and ready for firing in the kiln.

A leaf is painted and ready for firing in the kiln.

April 15, 2022

Michelle continues cutting glass. Pieces of panel #5 are laid out as pieces are cut.

David continues assembly and soldering of the completely cut out panels.

Painting and firing of the leaves continues apace with the cutiing.

 Michelle in the cutting room

Michelle in the cutting room

 Pieces of panel #5

Pieces of panel #5

 David working on the assembly of a panel

David working on the assembly of a panel

 A panel under construction

A panel under construction

 David hammers a nail while assembling a panel

David hammers a nail while assembling a panel

UNADJUSTEDNONRAW_thumb_b8cd.jpg
 Panels under construction

Panels under construction

 David soldering a panel after the assembly is complete

David soldering a panel after the assembly is complete

 Leaves having been fired in the kiln are waiting to be unloaded

Leaves having been fired in the kiln are waiting to be unloaded

 Panel #5 is completely cut out, awaiting assembly

Panel #5 is completely cut out, awaiting assembly

April 20. 2022

Michelle continues to cut glass.

David works on assemblies, making crates, cleaning panels and moving them to storage.

 Two panels moved outside to make room for the next assemblies

Two panels moved outside to make room for the next assemblies

 Detail of the stiffening pipe which is wired to the surface of the window in order to provide the rigidity necessary to move the panel into its opening on installation day.

Detail of the stiffening pipe which is wired to the surface of the window in order to provide the rigidity necessary to move the panel into its opening on installation day.

 Window with surface-mounted stiffening pipe.

Window with surface-mounted stiffening pipe.

 Michelle continues to cut out pieces

Michelle continues to cut out pieces

 Beginning the construction of the crates. Each panel will be installed into its crate for cleaning and then storage and finally delivery and installation.

Beginning the construction of the crates. Each panel will be installed into its crate for cleaning and then storage and finally delivery and installation.

 The first completed panel with stiffeniing pipe is installed into its crate.

The first completed panel with stiffeniing pipe is installed into its crate.

 Michelle continues cutting the hundreds of pieces of glass that make up the whole composition.

Michelle continues cutting the hundreds of pieces of glass that make up the whole composition.

 Three panels under construction.

Three panels under construction.

 David works on the assembly of a panel.

David works on the assembly of a panel.

April 21, 2022

Completion of the gold-leafed shin

Cutting continues

Assembly and glazing of panels.

Making the first crates

 The letter shin rendered in gold leaf.

The letter shin rendered in gold leaf.

 Working on the golden shin.

Working on the golden shin.

 Panels in various stages of completion with regard to the cutting of the glass.

Panels in various stages of completion with regard to the cutting of the glass.

 Michelle just keeps cranking out pieces.

Michelle just keeps cranking out pieces.

 Here is a panel covered in whiting, part of the process of glaizing the panels after assembly.

Here is a panel covered in whiting, part of the process of glaizing the panels after assembly.

 Here is a panel with the stiffening tube attached.

Here is a panel with the stiffening tube attached.

 Here’s David, putting windows together, like a machine.

Here’s David, putting windows together, like a machine.

April 27, 2022

Manipulating the 11’ long windows from the table to storage.

 Transfer to box

Transfer to box

 Detail

Detail

 Cleaning

Cleaning

 crating

crating

 Raising window in crate with winch

Raising window in crate with winch

 moving

moving

UNADJUSTEDNONRAW_thumb_b935.jpg
 storing

storing

May 11, 2022

Work continues. Michelle completing cutting out the seventh panel. David, assembling, soldering, glazing and building crates.

 Three panels nearing completion.

Three panels nearing completion.

 Four panels crowd the assembly room.

Four panels crowd the assembly room.

 Completed assembly, ready to crate.

Completed assembly, ready to crate.

 Getting ready to put on the border channel.

Getting ready to put on the border channel.

 Four windows completed and crated, ready for delivery and installation.

Four windows completed and crated, ready for delivery and installation.

 Panel covered in whiting, part of the glazing process.

Panel covered in whiting, part of the glazing process.

 Michelle lays out pieces as she cuts out the next panel.

Michelle lays out pieces as she cuts out the next panel.

 Pieces laid out  for panel number seven.

Pieces laid out for panel number seven.

May 19, 2022

Glass cutting continues. Placing an order for more glass. Assembly, crating and storing of the panels follows.

UNADJUSTEDNONRAW_thumb_b978.jpg
 Michelle works with the glass samples, getting ready to plzce a glass order.

Michelle works with the glass samples, getting ready to plzce a glass order.

 A partially assembled panel.

A partially assembled panel.

 A panel under construction.

A panel under construction.

 Getting ready to turn a panel over. Two boards are clamped together with the panel in the middle.

Getting ready to turn a panel over. Two boards are clamped together with the panel in the middle.

 Turning a panel over.

Turning a panel over.

 David attaches the stiffening pipe by twisting the copper wires tight.

David attaches the stiffening pipe by twisting the copper wires tight.

 A panel, in its box, is clamped to a table for cleaning.

A panel, in its box, is clamped to a table for cleaning.

 Wheeling a crated panel into storage.

Wheeling a crated panel into storage.

 Completed panels in storage.

Completed panels in storage.

May 27, 2022

Michelle completes panel #8 and begins cutting pieces for panel #9. David assembles panel #8. Seven panels completed and crated. Preparing the leaves for firing in the kiln contnues.

 Panel #7 in its crate is on the table for final cleaning.

Panel #7 in its crate is on the table for final cleaning.

 Panel #8 is layed out after cutting awaiting the return of the leaves from the kiln.

Panel #8 is layed out after cutting awaiting the return of the leaves from the kiln.

 Leaves are painted and ready to go into the kiln.

Leaves are painted and ready to go into the kiln.

 A set of leaves for panel #9 loaded into the kiln.

A set of leaves for panel #9 loaded into the kiln.

 A close up view of panel #8 under construction showing the leading prior to soldering.

A close up view of panel #8 under construction showing the leading prior to soldering.

 Seven completed panels in storage ready for installation.

Seven completed panels in storage ready for installation.

June 6, 2022

Work grinds forward, as panel #9 is completed, panel #10 is assembled and panel #11 is being cut out.

 Michelle give the thumbs up after moving panel #8 into storage.

Michelle give the thumbs up after moving panel #8 into storage.

 Michelle begins cutting out panel #9

Michelle begins cutting out panel #9

 Panel #9 partially assembled

Panel #9 partially assembled

 David works on the assembly of panel #10

David works on the assembly of panel #10

 David working on the assembly of panel #10

David working on the assembly of panel #10

 Beginning of the crate for panel #9

Beginning of the crate for panel #9

 Preparing the leaves of panel #10 for painting

Preparing the leaves of panel #10 for painting

 Panel #10 laid out during cutting with the leaves taken out for painting.

Panel #10 laid out during cutting with the leaves taken out for painting.

 Panel #9 in its crate on the table for final cleaning

Panel #9 in its crate on the table for final cleaning

 Michelle works on cutting out the pieces for panel #10

Michelle works on cutting out the pieces for panel #10

 Nine completed panels in their crates in storage.

Nine completed panels in their crates in storage.

 Panel #10 completely cut out and ready for assembly

Panel #10 completely cut out and ready for assembly

 Michelle begins cutting out panel #11

Michelle begins cutting out panel #11

 The first pieces fo panel #11 laid out on the table

The first pieces fo panel #11 laid out on the table

 Michelle continues to work on cutting glass for panel #11

Michelle continues to work on cutting glass for panel #11

June 9, 2022

David and Michelle are working on panels #10, #11, and #12.

 David completes panel #10, ready for crating

David completes panel #10, ready for crating

 Detail of panel #10

Detail of panel #10

 David is cleaning panel #10, prior to crating.

David is cleaning panel #10, prior to crating.

 Panel #11 under construction.

Panel #11 under construction.

 Ddtail of panel #10

Ddtail of panel #10

 Detail of panel #10

Detail of panel #10

 Panel #12, the last panel is being cut out.

Panel #12, the last panel is being cut out.

June 1 0, 2022

Michelle completes cutting out panel #12 finishing the glass cutting for the whole project.

David completes assembly and crating of panel #11 and begins assembly of panel #12.

Now begins planning for the transportatjon and installation of the entire project.

 Michelle completes cutting the last pieces of glass for the project.

Michelle completes cutting the last pieces of glass for the project.

 Eleven of the twelve panels are in their boxes ready for transportation to Davis.

Eleven of the twelve panels are in their boxes ready for transportation to Davis.

 Beginning of the assembly of the twelfth and last panel.

Beginning of the assembly of the twelfth and last panel.

June 17, 2022

Assembly of the final panel is completed.

 David adds the last piece to the assembly of the 12th and final panel.

David adds the last piece to the assembly of the 12th and final panel.

 Meausring the last piece of lead.

Meausring the last piece of lead.

 Cutting the final piece of lead border channel.

Cutting the final piece of lead border channel.

 David and Michelle Plachte-Zuieback

David and Michelle Plachte-Zuieback

Completion of the Fabrication

 The 12th panel on the table for final cleaning and crating.

The 12th panel on the table for final cleaning and crating.

 The final panel crated for delivery.

The final panel crated for delivery.

 All twelve panels in their boxes ready for transport.

All twelve panels in their boxes ready for transport.

June 25, 2022

Planning the loading of the truck for the delivery of the windows to Bet Haverim.

 Backed up to the storage room where the completed windows have been stored in their individual crates.

Backed up to the storage room where the completed windows have been stored in their individual crates.

 Moving the truck out to eye ball the loading plan.

Moving the truck out to eye ball the loading plan.

 Truck with six of the twelve windows loaded for transport to Santa Rosa, there to be staged until the July 5th delivery to Davis

Truck with six of the twelve windows loaded for transport to Santa Rosa, there to be staged until the July 5th delivery to Davis

June 29, 2022

Transporting the finished panels to the job site.

 The second truck load of window panels and tools for the installation leaves the Sherwood Ranch Studio.

The second truck load of window panels and tools for the installation leaves the Sherwood Ranch Studio.

July 3, 2022

Delivery of equipment and the first six windows to Bet Haverim

 Our truck loaded with windows and install materials and equipment arrives at Bet Haverim.

Our truck loaded with windows and install materials and equipment arrives at Bet Haverim.

 Unloading the truck into the sanctuary.

Unloading the truck into the sanctuary.

July 11, 2022

Installation!

 David and Clint working on the install

David and Clint working on the install

 David putting on finishing touches on one of the panels

David putting on finishing touches on one of the panels

 All the panels on the left side installed

All the panels on the left side installed

 David touches up the paint on the stops.

David touches up the paint on the stops.

 Windows on the left side

Windows on the left side

 Windows on the left side

Windows on the left side

 Transferring a panel from the box to the opening

Transferring a panel from the box to the opening

 Transfering a panel

Transfering a panel

IMG_0031 2.jpg
IMG_0038.jpg
 Install team

Install team

 Windows on the right side

Windows on the right side

IMG_0057.jpg
 Windows on the right side

Windows on the right side

 Michelle Plachte=Zuieback, artist

Michelle Plachte=Zuieback, artist

UNADJUSTEDNONRAW_thumb_baf4.jpg
UNADJUSTEDNONRAW_thumb_bafe.jpg
prev / next
Back to Bet Haverim Stained Glass Project Journal
5
Bet Haverim
 Working on the patterns
15
Making the Pattern
 Michelle cuts the first piece of glass.
12
Glass Cutting Begins
6
Cutting Continues
 Michelle working in her studio
8
March 24, 2022
 Michelle bends over the cutting table while she cuts out the leaves.
6
April 3, 2022
6
Assembly Begins
 Cutting continues.
8
April 8, 2022
 Michelle applies paint to the leaves after the composition and lay out has been burnished on and cut out with the xacto knife.
4
April 12, 2022
 Michelle in the cutting room
10
April 15, 2022
 Two panels moved outside to make room for the next assemblies
9
April 20. 2022
 The letter shin rendered in gold leaf.
7
April 21, 2022
 Transfer to box
8
April 27, 2022
8
May 11, 2022
10
May 19, 2022
 Panel #7 in its crate is on the table for final cleaning.
6
May 27, 2022
 Michelle give the thumbs up after moving panel #8 into storage.
15
June 6, 2022
 Michelle begins to cut out panel #12
7
June 9, 2022
 Michelle completes cutting the last pieces of glass for the project.
3
June 1 0, 2022
 David adds the last piece to the assembly of the 12th and final panel.
4
June 17, 2022
 The 12th panel on the table for final cleaning and crating.
3
Completion of the Fabrication
 Backed up to the storage room where the completed windows have been stored in their individual crates.
3
June 25, 2022
 The second truck load of window panels and tools for the installation leaves the Sherwood Ranch Studio.
1
June 29, 2022
 Our truck loaded with windows and install materials and equipment arrives at Bet Haverim.
2
July 3, 2022
 David and Clint working on the install
17
July 11, 2022